Lamb Street, Murgon-CBD Footpath, Kerb and Channel Replacement

Back

Council is pleased to advise the progress of the replacement of Murgon’s CBD footpath along Lamb Street (between Krebs and Gore Street’s).

funded through the Queensland Government’s 2019-21 Works for Queensland program (W4Q R3) and South Burnett Regional Council. Detailed planning has preceded works in order to ensure all businesses can remain operational during the construction period.  
 
With the completion of all major demolition and concreting works, Council acknowledges the outstanding cooperation of the Murgon business community. Remaining spray pave colour application works are scheduled to occur during standard business hours, with business entrances undertaken after COB. Image of completed works can be seen below in image- Completed spray pave.

Details of activities planned for the week commencing Thursday 30 July are outlined below and highlighted in the “Image – Plan of works”. GREEN Sections are considered complete.   

Week commencing Thursday 30 July 2020

RED Southern spray pave concrete- working adjacent to The Australian Hotel.

Motorists and pedestrians are requested to travel with extreme care, to drive to the prevailing road conditions and to adhere to signage. Council apologises for any inconvenience caused and thanks you for your patience whilst works are in progress. 

Latest update 3007

Image- Plan of works

The Murgon CBD Footpath project has been funded by the Queensland Government’s Works for Queensland program and South Burnett Regional Council.

 

Should you have any questions or concerns regarding any facets of the project, please contact Council’s Infrastructure team by phone on (07) 4189 9100 or email