UPDATE - Gravel Resheeting Works – August & September

Back

South Burnett Regional Council advises that gravel resheeting works, funded through the Roads to Recovery programme, continue throughout the region during August and September 2020, weather permitting.

Gravel resheeting is scheduled for the following locations:

  • Burra Burri Road, Chahpingah – expected to commence early August and take approximately 6 weeks, with works finishing mid-late September;
  • Franklins Road, Coolabunia – expected to commence early August and take approximately 3 weeks, with works finishing late August;
  • Glenmore Road, Sandy Ridges – expected to commence late August and take approximately 4 weeks, with works finishing mid-late September;
  • Friebergs Road, Warnung – expected to commence early August and take approximately 3 weeks, with works finishing late August.

In order to provide a safe work environment, the work areas will be controlled by signage or with traffic controllers as required. Local access to properties within the work area will be permitted, however some delays may occur. Motorists are requested to travel with extreme care, to drive to the prevailing conditions and to adhere to signage.

Council apologises for any inconvenience caused and thanks you for your patience whilst works are in progress.

Council’s Works programme is published and available to view on Council’s website.

For further information regarding the gravel resheeting programme or upgrade works contact Council’s Works team on 4189 9100 or email Council.