UPDATE - Gravel Resheeting Works - January
South Burnett Regional Council advises that gravel resheeting works will commence in these locations, weather permitting:
• Greenwood Creek Road, from Mercer Springate Road intersection to end, on 18 January 2021. These works are expected to be undertaken over a 10-day period.
• Mercer Springate Road early February 2021 with an expected duration of 15 days.
In order to provide a safe work environment, the work areas will be controlled by signage or with traffic controllers as required.
Motorists are requested to travel with extreme care, driving to the prevailing road conditions and to adhere to signage.
Council apologises for any inconvenience caused and thanks you for your patience whilst works are in progress.