Blackbutt CBD Streetscape and Footpath Upgrade - Update
Construction works are now underway in Blackbutt as the CBD area undergoes revitalisation and infrastructure improvements.
Recent weather events have provided challenges with rain causing delays in the initial excavation. Weather conditions are expected to improve, allowing construction to recommence Monday 28th February.
The construction program continuing over the next two weeks will see the construction of subsoil drains and gravel pavements where new kerb and channel will be constructed as works progress.
While excavation is underway new water supply services will be provided to properties along the area of immediate works. These works will require the testing of water main valves and connections. It is anticipated these works may cause minor delays as testing and connections occur. Lengthy delays in water supply are not expected. All businesses and properties will be provided suitable notice prior to any disruption to water supply. Where possible connections may be completed out of business hours.
These works shall continue west along Coulson Street between Muir Street and the frontage of Les Muller Park allowing the preparation to continue for the new kerb and channel planned for the week ending 12 March 2022, weather permitting.
Construction activity at times may provide noise from machinery and equipment, some restrictions to vehicle parking and pedestrian access for public safety, however these impacts will be limited and allow continual business access as construction progresses along Coulson Street.
Site works and construction activity will be performed Monday to Friday – 6:30am – 5:00pm and Saturday – 7:00am - 5:00pm. The project is expected to be completed by June 2022.
For further information regarding the project, please contact Council’s Infrastructure team on 4189 9100 or email info@sbrc.qld.gov.au.