Blackbutt CBD Streetscape and Footpath Upgrade - Update 14 March 2022

Back

Works are continuing to progress the Blackbutt CBD Streetscape and Footpath Upgrade. Recent weather events continue to provide challenges in the progress of works.

Works are continuing to progress the Blackbutt CBD Streetscape and Footpath Upgrade.  Recent weather events continue to provide challenges in the progress of works, however amendments to the construction methodology have limited disruption to the schedule of works and the original program timelines.

The demolition of the old kerb and channel within the first zone of works from the intersection of Muir Street and Coulson Street has progressed along Coulson Street toward the frontage of Les Muller Park and has now been completed.

The construction of the new subsoil drainage in this area has also been completed allowing the final preparation of the base material for the new kerb and channel to be constructed which is scheduled for Monday 14 March 2022.  The ability to access property and business driveways will be impacted for a limited period whilst these works are undertaken.  Council apologises for any inconvenience and will endeavour to keep impacted businesses updated.

The installation of new water service connections to properties and business are expected to commence Tuesday 15 March 2022.  Residents and businesses are advised these works may require some disruption to water supply.  Where possible, connections will occur outside of business hours to limit the impact and disruption of supply.  These works will progressively occur over several days.  Notice will be provided to impacted properties and businesses prior to any service disruption.

Some restrictions to vehicle parking and pedestrian access for public safety are expected, however these impacts will be limited and allow business access as construction progresses along Coulson Street. Construction noise is expected through the course of these works.

Site works and construction activity will be performed Monday to Friday – 6:30am – 5:00pm and Saturday – 7:00am - 5:00pm, with the project expecting to be completed by June 2022.

For further information regarding the project, please contact Council’s Infrastructure team on (07) 4189 9100 or email info@southburnett.qld.gov.au.