Search our site...

Blackbutt CBD Streetscape and Footpath Upgrade – Update 20th May 2022

Back

The new concrete footpath is now complete within the first and second zones of works along Roy Emerson Way (Coulson Street) from the intersection of Muir Street and Coulson Street to Les Muller Park.

Works have recommenced this week following a period of wet weather with the completion of the concrete footpath and the road pavement in the second work zone. The new concrete invert at the John Street intersection has also been installed. The Blackbutt CBD Streetscape and Footpath Upgrade on track with the original program timelines for completion.

Priming of the road pavement in the second work zone will be completed this week. Asphalt surfacing of the pavement in the second work zone and surface grinding of the existing concrete footpath is planned to be completed next week. The ability for vehicle access to property and business driveways will be impacted for short periods while these works occur. Council apologises for any inconvenience and will endeavour to keep impacted businesses and properties updated as these works progress.

Works in the central median area are also scheduled to commence next week with saw cutting of bitumen and removal of garden beds and pavement areas.

John Street intersection is planned to be reopened to traffic late next week.

To maintain public safety some restrictions to vehicle parking and pedestrian access are expected, however these impacts will be limited and allow continual business access as construction progresses along Coulson Street. Construction noise is expected through the course of these works.
Site works and construction activity will be performed Monday to Friday – 6:30am – 5:00pm and Saturday – 7:00am - 5:00pm, with the project expecting to be completed by June 2022.

For further information regarding the project, please contact Council’s Infrastructure team on (07) 4189 9100 or email info@sbrc.qld.gov.au.

Blackbutt