UPDATE - Lamb Street Murgon-CBD Footpath, Kerb and Channel Replacement

Back

Council is pleased to advise that the replacement of Murgon’s CBD footpath, along Lamb Street (between Krebs and Gore Streets), continues with the demolition of the existing footpath progressing.

Detailed planning has preceded works in order to ensure all business can remain operational during the construction.

The majority of works are scheduled to be delivered at night between 6pm-6am, with additional supporting tasks being undertaken during standard working hours as required. Last week saw the completion of footpath demolition in the section adjacent to the intersection of Lamb and Gore Streets.

Details of activities planned for the weeks commencing Sunday 24 February and Sunday 1 March 2020 are outlined below, weather permitting:

Week commencing Sunday 23 February 2020

A new demolition work zone will be set up between the Dog Wash and the Bakery on Sunday evening from 6:00pm (highlighted in yellow) – refer image 1.

Concrete pours at the intersection of Krebs and Lamb Streets will commence Monday evening at 6:00pm and continue during night works. These works are scheduled to be completed by the end of the week.

Concreting works will finish Friday morning allowing for weekend activities. These works will result in the partial closure of the service lane and parking areas directly adjacent to the work zones. Works occurring during standard working hours will include surveying, formwork and communication infrastructure relocation.

Week commencing Sunday 1 March 2020

Stage 1 demolition and earthworks (highlighted in yellow) are scheduled to be complete – refer image 1. Stage 2 demolition works (highlighted in red) are scheduled to commence – refer image 2, with businesses located between Encore Pilates and Advice Partners being affected.

Concreting works will include the pouring of new pavement adjacent to the intersection of Lamb and Gore Streets early in the week, moving to the newly demolished sections as mentioned above.

Motorists and pedestrians are requested to travel with extreme care, to drive to the prevailing road conditions and to adhere to signage.  Council apologises for any inconvenience caused and thanks you for your patience whilst works are in progress.

Should you have any questions or concerns regarding any facets of the project, please contact Council’s Infrastructure team by phone on 4189 9100 or email info@southburnett.qld.gov.au.

The Murgon CBD Footpath project has been funded by the Queensland Government’s Works for Queensland program

 