Latest news in Roads & Drainage
-
Temporary Closure of Laneway beside Kingaroy Library
Council advises that due to unforeseen circumstances the laneway beside the Kingaroy library will be closed today Thursday 7 July 2022.
-
Blackbutt CBD Streetscape and Footpath Upgrade – Update 29 April 2022
The new concrete footpath is now complete within the first zone of works along Coulson Street from the intersection of Muir Street and Coulson Street to Les Muller Park.
-
Temporary Road Closure – John Street Blackbutt
Temporary closure of John Street at the intersection with Coulson Street is planned to commence Tuesday 3 May to allow reconstruction of the concrete invert in John Street.
-
Kingaroy Street and Adjoining Intersections- Asphalt Works
Works to reinstate the road surface within Kingaroy Street and adjoining intersections of Haly Street and Alford Street will commence on 3 May and be completed on or before 10 May.
-
Glendon Street/Markwell Street Blackspot Funded Project
The Blackspot Funded Project, designed to improve the safety within the Glendon Street/Markwell Street roundabout, will be commencing on the morning of Tuesday, 26 April 2022.
-
South Burnett Local Disaster Management Group (LDMG) update #6
The LDMG continues to meet and wishes to advise that a number of roads have re-opened across the region, however there is still extensive flooding across the major streams in Barkers Ck & Barambah Ck.
-
Blackbutt CBD Streetscape and Footpath Upgrade - Update
Construction works are now underway in Blackbutt as the CBD area undergoes revitalisation and infrastructure improvements.
-
South Burnett Local Disaster Management Group (LDMG) update #1
The South Burnett Local Disaster Management Group (SBLDMG) has moved its status to “Lean Forward” this morning.
-
Gravel Resheeting works - Alice Creek Road, Alice Creek
South Burnett Regional Council wishes to advise that gravel resheeting works are due to commence week beginning Monday 21 February 2022 on Alice Creek Road, Alice Creek, weather permitting.
-
Work to Commence on Kumbia Road, Kumbia
South Burnett Regional Council wishes to advise that works are due to commence week beginning Monday 21 February 2022 on Kumbia Road, Kumbia, weather permitting.
-
Notice of Works - Oliver Bond Street, Kingaroy
South Burnett Regional Council wishes to advise that works have commenced on Oliver Bond Street, Kingaroy.
-
Blackbutt CBD Streetscape and Footpath Upgrade
South Burnett Regional Council is proud to announce the commencement of the Blackbutt CBD Streetscape and Footpath Upgrade with works commencing Wednesday 16 February 2022.
-
Disaster Recovery Funding Arrangements (DRFA)
South Burnett Regional Council is pleased to announce that the South Burnett region has been activated
-
South Burnett Regional Council Update – ex-Tropical Cyclone Seth from 7 – 10 January 2022
South Burnett Regional Council crews have been activated during and since the heavy rainfall in the Gympie Region catchments impacting the South Burnett
-
KTP Update - Schedule of Works for January 2022 - Kingaroy Street
The Kingaroy Transformation Project will recommence on 4 January 2022, with the reconstruction of Kingaroy Street between Alford Street and Haly Street.